KHURJA SUPER THERMAL POWER PROJECT

  • Location                      : Near Khurja, Distt: Bulandshahr, UP
    Proposed Capacity    : 2 x 660 MW (1320 MW)
    Technology                 : Coal based Supercritical Thermal Power Project
    Fuel                              : Coal
    Fuel Requirement       : 5.6 MTPA
    Fuel Source                 : Amelia Coal Mine (M.P.)
    Grade of Coal              : G9
    Average GCV               : 4746 kcal/kg
    Fuel Transportation     : By Indian Railway Network
    Water Source                : Upper Ganga Canal
    C.W. System                 : Recirculating type CW system with IDCT
    Power Evacuation        : Power generated from plant shall be evacuated through 400 kV Substation
    Steam turbines             : 2 Nos.
    Coal Fired Boilers        : 2 Nos.
    Chimney (Twin flue)     : 1 No.   
     
     
    Special Project Features
    The Project is based on Ultra Supercritical Technology, Closed Cycle Water Recirculation System for Zero Discharge Concept, equipped with Flue Gas Desulphurization (FGD), Selective Catalytic Reduction (SCR) and Upgraded Electrostatic Precipitators (ESP) having efficiency more than 99% to control SOx, NOx and Particulate Matter respectively, conceptualized to perform even better than the latest emission norms of MoEF&CC.
     




Updated on : 30/06/2021