ULTRA MEGA RENEWABLE ENERGY POWER PARKS(Through JV)

  •  
    THDCIL has diversified into Renewable Energy and has already commissioned 113 MW Wind Power Projects in Gujarat (50 MW at Patan and 63 MW at Dwarka) and 50 MW Solar Power Project in Kerala.
     
    Under the Ultra Mega Solar Power Scheme of Govt of India, MNRE has allotted THDCIL to develop UMREPPs through SPV/JVC in the state of Uttar Pradesh and Rajasthan. The capacity of Solar Parks to be developed in UP is 2000 MW and Rajasthan 1500 MW.Status of the UMREPPs is as under -
    1. Uttar Pradesh:
     
    A Joint Venture Company namely TUSCO Limited between THDCIL and UPNEDA has been registered on 12.09.20 to develop 2000 MW Ultra Mega Renewable Energy Power Parks in U.P. In-principle approval for the entire 2000 MW Solar Power Parks has been accorded by MNRE.

    i. 600 MW Solar Power Park in Tehsil Garautha, district Jhansi
    1. In-principle approval for setting up of the Solar Power Park has been accorded by MNRE on 13.10.20.
    2. In order to set up the solar park, the land of about 3023 acre(Govt. Land- 242 acre and Private Land-2781 acre of 1405 farmers) has been identified in district Jhansi.
    3. DM has finalized the Lease Rent for the identified land
    4. DPR of Jhansi Solar Park has been submitted to both SECI and MNRE, which is under finalization.
    5. Signing of Lease agreements for private land with the farmers is in progress

      ii. 600 MW Solar Power Park in Tehsil Talbehat, district Lalitpur
    1. In-principle approval for setting up of the Solar Power Park has been accorded by MNRE on 13.10.20.
    2. To set up the solar park, the land of about 2800acre(Govt. Land- 977 acre and Private Land-1823 acre of 1240 farmers) has been identified in district Lalitpur.
    3. DM has finalized the Lease Rent for the identified land.
    4. DPR of the Solar Park has been submitted to both SECI and MNRE, which is under finalization.
    5. Signing of Lease agreements for private land with the farmers is in progress.
     
    iii. 800 MW Solar Power Park in Tehsil Mau, district Chitrakoot
    1. In-principle approval for setting up of the Solar Power Park has been accorded by MNRE on 18.08.21.
    2. To set up the solar park, the land of about 3005acre (Govt. Land- 830 acre and Private Land-2175 acre of about 1250 farmers) has been identified and balance 1000 acre is under identification.
    3. DM has finalized the Lease Rent for the identified land.
    4. Obtaining Expression of Interest (EoI)/ consent with the farmers is in progress.


             II.Rajasthan:
     
    THDCIL has submitted the requisite   Board   Resolution   of   the Corporation to Rajasthan Renewable Energy Corporation (RRECL) and Principal Secretary, Govt. of Rajasthan on 20/01/2020 for allocation of 1500 MW UMREPP in Rajasthan to THDCIL and signing of the necessary MOU with RRECL.
     
    The signing of the necessary MOU with RRECL and allocation of the land for the Power Parks are awaited from Government of Rajasthan.
     




Updated on : 20/09/2021