Tehri Hydro Power Complex (2400 MW)
Tehri Hydro Power Complex (HPC) is a multipurpose hydro power complex developed by THDC India Limited (THDCIL) on the Bhagirathi River in Uttarakhand. With a total installed capacity of 2,400 MW, the complex comprises Tehri HPP (1,000 MW), Koteshwar HEP (400 MW) and Tehri Pumped Storage Plant (1,000 MW). The complex supports peak power generation, irrigation and drinking-water requirements of the region and contributes significantly to grid balancing and renewable energy integration.

 

Tehri Hydro Power Plant (1000MW)
Tehri Hydro Power Plant (HPP) is a storage-based hydropower project comprising a 260.5 m high earth and rockfill dam across the River Bhagirathi and an underground powerhouse equipped with four 250 MW Francis turbine-generator units. Commissioned during 2006–07, Tehri HPP provides valuable peaking power to the Northern region of the country and supports the irrigation and drinking-water requirements in the region. The reservoir has also contributed to flood moderation during periods of heavy rainfall.

 

GENERAL FEATURES

ParticularsDetails
Installed Capacity1000 MW (4X250 MW)
LocationTehri Garhwal, Uttarakhand
Design Energy2797 MU
Commercial Operation Date
  • Unit-4: 22.09.2006
  • Unit-3: 09.11.2006
  • Unit-2: 30.03.2007
  • Unit-1: 09.07.2007 
Beneficiary States/ UTsUttar Pradesh, Uttarakhand, Punjab, Rajasthan, Delhi, Jammu & Kashmir, Chandigarh, Haryana and Himachal Pradesh

KEY TECHNICAL FEATURES

ParticularsDetails
Dam Type      Earth and Rockfill Dam
Dam Height    260.5 m
Dam Length at Top    575 m
Gross Reservoir Storage    3,540 MCM
Live Storage    2,615 MCM
Full Reservoir Level (FRL)    EL 830 m
Spillway    3-bay Chute Spillway + 2 Right Bank Shaft Spillways + 2 Left Bank Shaft Spillways
Head Race Tunnels    2 x 8.5 m diameter; 1,634 m total length
Penstocks    4 × 5.75 m diameter; 1,040 m total length
Tail Race Tunnels2 × 9.0 m diameter, 862.5 m & 747.5 m long
PowerhouseUnderground, Left Bank
Generating Units4 × 250 MW
Turbine TypeFrancis
Maximum / Minimum Head    231.5 m / 127.5 m
Design Head188 m
Rated Discharge per Unit145 cumecs
Switchyard    400 kV Indoor SF₆ Switchgear
Benefits from the Tehri Hydro Power Complex
· Addition to the installed generating capacity in the Northern Region;
(1000 MW on completion of Tehri Stage-I);
2400 MW
  • Annual energy availability (Peaking)
    (2797 MU on completion of Tehri Stage-I)
5220 MU
  • Irrigation (additional)
2.70 Lac.ha.
  • Stabilisation of existing irrigation
    (besides above)
6.04 Lac.ha.
  • Additional Generation in downstream Projects
200 MU
  • 300 Cusecs (162 million gallons per day) of drinking water for Delhi which will meet the requirements of about 40 lac people.
  • In addition, 200 Cusecs (108 million gallons per day) of drinking water for towns and villages of U.P. which will meet the requirement of 30 Lac people.
  • Flood Moderation
· Integrated development of Garhwal region, including construction of a new hill station town with provision of all civic facilities; improved communication, education, health, tourism, development of horticultures, fisheries, and afforestation of the region.
S.No.DescriptionGeneration (MU)
1Generation during August 2026621.74
2Cumulative Generation during FY 2026-27 (up to August 2026)1217.42